The Continuity Registration is a process that passes through several phases. The fourth phase is called Continuous Operation, where it will be defined the Continuity Awareness (Education and Training), Review and Continuity Audit, the Tests about the continuity, and its Invocation. This functionality allows viewing the events of service continuity tests.

## Before getting started

- [x] Make sure there is a defined service in a Portfolio and Catalog Management  &#x20;process.
- [x] It is fundamental to first have registered the Continuity Registration, the  &#x20;policy and the project of continuity of service already defined.
- [x] Also, make sure to have the scope, vital functions, business impact analysis, risk evaluation,  &#x20;strategy, plan, organizational planning, the strategy of tests of continuity  &#x20;awareness already registered and the audit and review of the continuity already  &#x20;done.
- [x] It is necessary to have previously registered the threat and the threat categories both  &#x20;linked to each other. Also, the risk and the risk  &#x20;category.
- [x] It is equally essential to have registered the automatic actions to the incident,  &#x20;request and procedure about the Event Management.

## Procedure

1. Access the functionality through the main menu `Processes > Continuity    Management > Continuity`;
2. Find the continuity you want to view the tests event and click on "**Advance**";
3. In **Continuous Operation**, click on "**Test**";
4. It will be presented a calendar with events of tests, created during the   &#x20;implementation, which we will name after tests. These events can be viewed by   &#x20;month, week, or day. To set the type of view, click on one of the buttons   &#x20;above the calendar: "**Month**", "**Week**" or "**Day**";
5. Click on the test event and:
   1. Complete the fields about the main information of the event;
   2. Click on the tab "**Group**" and then on "**Add Group**" to search and link the      &#x20;group you want;
   3. Click on the tab "**Employee**" and then on "Add Employee" to search and      &#x20;link the employee you want;
   4. Click on the tab "**Test Evidence**" and then on "**Add test evidence**" to      &#x20;search and link it to a shred of test evidence already existed or click on "**Create test      &#x20;evidence**" to create a new knowledge, detailing the evidence;
   5. Click on the tab "**Test Plan**" and then on "**Add test plan**" to search and      &#x20;link a test plan.
6. Click on "**Save**" on the test calendar to apply the changes made.

## What to do next

After verifying the continuity test calendar, if necessary, it is possible to invocate the continuity, action of the fourth&#x20;phase of the complete registration of the Continuity called Continuous Operation.